Wind Systems Magazine

May 23, 2013

Share

RELATED ARTICLES

CONSTRUCTION

Micropiles are versatile enough to function either as a new...

 

Best Practices for Electrical Startups

During wind farm construction, electrical systems testing...

 

CONSTRUCTION

Mass stabilization is a soil mixing technology for treating...

 

Tracking Renewable Talent

From green power brokers, attorneys, and financial experts...

 

CONSTRUCTION

Compaction grouting is the only soil improvement technique...

 

Harnessing Digital Elevation Data

Intermap Technologies explains how using terrain...

 

CONSTRUCTION

When the upper soil structure is too weak to support a wind...

 

CONSTRUCTION

Mass stabilization is a soil mixing technology for treating...

 

Harnessing Digital Elevation Data

Intermap Technologies explains how using terrain...

 

Vibration-Based Wind Tower Foundation Design

Wind towers must sustain continuous vibration-induced...

 

CONSTRUCTION

Integrating construction engineering into wind facility...

 

CONSTRUCTION

When the upper soil structure is too weak to support a wind...

 

Innovating Wind Turbine Performance with BPM Software for Case Management

Dynamic Case Management (DCM) gives EDPR North America an...

 

CONSTRUCTION

Going green doesn’t necessarily mean that you must erect...

 

CONSTRUCTION

Crane business is booming in Texas and this company...

 

CONSTRUCTION

Wind speeds change at various heights, making hoisting...

 

CONSTRUCTION

Mass stabilization is a soil mixing technology for treating...

 

TECHNOLOGY

Fluid-structure interactions in floating offshore wind...

 

CONSTRUCTION

Consisting of concrete columns installed through weak...

 

CONSTRUCTION

Micropiles are versatile enough to function either as a new...

 

Making the Cut With HGG Profiling Machines

The Leica Absolute Tracker monitors cutting of wind turbine...

 

Forest Sites Demand a Differentiated Approach

Alternative turbine location sites in Germany have...

 

LOGISTICS

Reporting straight from the jobsite, the author relates...

 

Wind Turbine Capacity Frontier From SCADA

The wind industry is experiencing rapid growth across the...

 

A Foundation for Success

Rammed Aggregate Pier systems by Geopier are now commonly...

 

Protecting Wind Energy Investments

Wind developers should look for an insurance carrier that...

 

CONSTRUCTION

A proven technique for stopping or reducing settlement,...

 

CONSTRUCTION

When conducting site remediation, jet grouting is one...

 

CONSTRUCTION

When performed properly, vibro compaction is an efficient...

 

Patenting the Winds of Innovation

Companies are racing to protect their wind turbine...

 

Maintenance Profile: Eaton Corporation

From maintenance services, to turnkey substation...

 

The Hidden Costs of Ownership

By understanding—and addressing—a host of related...

 

CONSTRUCTION

Wind speeds change at various heights, making hoisting...

 

Modular Foundations for Small Wind

Innovative new foundations by Oldcastle Precast decrease...

 

CONSTRUCTION

Performed properly, a mat foundation bearing on aggregate...

 

Archives > October 2012 > CONSTRUCTION

CONSTRUCTION

By: Julian Bell

 

Preconstruction planning on wind projects yields budgetary benefits for developers.

 

One of the most valuable tools that an owner or developer of wind projects has in its planning toolbox is a good preconstruction value engineering methodology. Developers can realize large short- and long-term economic payback if they commit time and resources to value engineering each aspect of the engineering and construction of a wind project early in the development process. Engaging an experienced design/build contractor at an early stage to perform this value engineering analysis insures that a project is designed in a way that maximizes long-term energy production and short-term capital costs for construction.


Wind project construction is made up of five main areas: (1) civil infrastructure-roads, crane pads, crane paths; (2) electrical collection system-underground and overhead; (3) wind turbine foundations; (4) substation and interconnection facilities; and (5) wind turbine erection. By gathering the right information at an early stage, each of these areas can be optimized to achieve the highest quality with the lowest cost.


Effective preconstruction planning depends upon the early accumulation of basic, but critical, information. Developers should make every effort to develop the following information at the earliest possible stage in the development process:


(1) Geotechnical Information: Solid geotechnical information is the underpinning for the effective design of a number of major wind farm components: (a) wind turbine foundations; (b) roads, crane pads and paths; and (c) underground electrical collection system. Wind turbine foundations make up a significant portion of the overall project cost, and represent one of the most critical risk management items. No shortcuts should be taken in determining the proper wind turbine foundation design. This design begins with a complete understanding of the geotechnical characteristics of the project site. On many projects, the geotechnical investigation is postponed until late in the project development process and costs are budgeted based upon assumed geotechnical conditions.


(2) Topographical/geographic Information: Further optimization of the civil infrastructure (wind turbine locations, project access and turbine string road locations, crane path locations) and the electrical collection system (location) requires detailed knowledge of the physical properties of the project site (i.e. topography, wetlands, existing road system, existing structures, underground pipelines, etc.). In addition, this optimization requires knowledge of the landowner, governmental and regulatory rules and regulations that will apply to the project (easement restrictions, setbacks, road agreements). 


(3) Interconnection information and utility requirements: Substation and interconnection facility costs comprise a large percentage of the overall project costs. Accurate interconnection information is critical to the design of the project substation and interconnection facilities.


Ultimately, substation and interconnection facilities design, optimization and pricing is finalized after the Interconnection Agreement (“IA”) is available. The IA typically includes the Facility Study, which specifies the material and equipment that the utility will require for interconnection with the transmission line. However, early stage planning and cost estimating can be done with some basic information: (a) interconnection voltage; (b) point of interconnection location; (c) available routing for transmission line from the project site to the POI, if applicable. The interconnection voltage will help to determine the substation design and the main power transformer specifications.


(4) Turbine Selection and Delivery Timeframe: Early stage development of the project schedule and pricing is highly dependent upon the wind turbine selection and the anticipated delivery dates and delivery rate. The wind turbine loading helps to determine the foundation type and size. The selection of the proper main erection crane (itself a major cost and schedule component) depends upon the turbine type, weight, and hub height. The timing and rate of the wind turbine component deliveries helps to determine the unloading crew size and necessary equipment to mobilize to site (e.g. number of unloading crews, number of unloading cranes and ancillary equipment).


The project schedule must be developed such that the construction of project infrastructure is not impacted by the thaw restrictions, especially when turbine component deliveries are timed immediately before or after thaw restrictions are placed, or lifted.  


Experienced design/build contractors can use their construction expertise to assist project developers in the proper design of all major wind project construction components. Early engagement of a contractor to employ a methodical value engineering analysis to develop preliminary project designs can be the difference between an economically viable project, and one that is left on the drawing boards. 

 

 

About The Author
Julian Bell

is the director of preconstruction for Signal Energy Constructors. For more information, visit www.signalenergy.com.

 

 

Wind Systems is a trademark of Media Solutions, Inc, copyright 2002-2010.

Wind Systems and all contents are properties of Media Solutions, Inc.