Wind Systems Magazine

May 21, 2013

Share

RELATED ARTICLES

A Foundation for Success

Rammed Aggregate Pier systems by Geopier are now commonly...

 

Maintenance Profile: Eaton Corporation

From maintenance services, to turnkey substation...

 

CONSTRUCTION

Crane business is booming in Texas and this company...

 

A Model for Offshore Innovation

As offshore development begins in the United States,...

 

Company Profile: GL Garrad Hassan

With roots in academia and R&D this company offers...

 

CONSTRUCTION

Proper contingency planning for weather, materials...

 

LOGISTICS

In this installment we discuss the Seven Laws of Supply...

 

CONSTRUCTION

Production Tax Credit extension may lead to additional...

 

External Background Noise in Wind Farms

Optimizing wind farm operating conditions by improving the...

 

CONSTRUCTION

Lack of proper planning or poor scope definition during...

 

CONSTRUCTION

Preconstruction planning on wind projects yields budgetary...

 

CONSTRUCTION

Wind turbines may seem alike from a distance in terms of...

 

CONSTRUCTION

It’s strange to think about, but the very winds that make...

 

CONSTRUCTION

There is both science and math at the core of all rigging...

 

Company Profile: NAES Corp.

Providing engineering, construction, turbine repair, and...

 

CONSTRUCTION

Going green doesn’t necessarily mean that you must erect...

 

CONSTRUCTION

Identifying broken tiles usually calls for close...

 

Construction Profile: White Construction

In the top tier of wind farm construction experts, this...

 

Providing Concrete Evidence

A new telescopic truck-mounted conveyor belt system from...

 

CONSTRUCTION

Preconstruction planning on wind projects yields budgetary...

 

CONSTRUCTION

Once your project has been cleared to proceed, which...

 

Concrete Proof: The Majestic Wind Farm

By using the Putzmeister Telebelt conveyor to transport...

 

LOGISTICS

If properly prepared, trained, and equipped, people – not...

 

Construction Profile: Geopier Foundation Co.

Whether strengthening access roads or the soil beneath...

 

CONSTRUCTION

Understanding the importance of field tiles and identifying...

 

A Case for Wind Farm Construction

An in-depth review of the construction phase of the Wild...

 

CONSTRUCTION

Crane business is booming in Texas and this company...

 

Patenting the Winds of Innovation

Companies are racing to protect their wind turbine...

 

CONSTRUCTION

Wind speeds change at various heights, making hoisting...

 

Innovating Wind Turbine Performance with BPM Software for Case Management

Dynamic Case Management (DCM) gives EDPR North America an...

 

Best Practices for Electrical Startups

During wind farm construction, electrical systems testing...

 

Company Profile: Global Energy Services

Strategically located in key renewable energy markets in...

 

CONSTRUCTION

Going green doesn’t necessarily mean that you must erect...

 

Collaboration in Wind Farm Construction

Wind industry professionals understand the high degree of...

 

CONSTRUCTION

Clarifying scope definition prior to beginning a project...

 

Archives > June 2012 > CONSTRUCTION

CONSTRUCTION

By: Chris Martin

 

Many factors play a role in successfully coordinating crane service for wind park maintenance.

 

In the past few months we have discussed crane rigging, types of cranes, and how to remove blades. This month we will be taking a step back and discussing the behind the scenes of wind park maintenance. Clients will ask if we can get the crane on-site in a few days or within a few hours. We always say yes and meet our promise. But dispatching a crane is not easy. It is actually quite a difficult process.

There are so many factors behind the scenes that determine when and how we get a crane on-site. Every day we are faced with different challenges; challenges that change daily due to employee locations, weather, previous and future crane jobs, and actual erection time.

Employee locations change all the time. We have drivers spread out all over the Southwest picking up and dropping loads off. With our Manitowoc model 16000 we need 18 truckloads to get the 500,000 lb. crane on-site. The coordination required to make this happen is immense. We have to coordinate with all of our branches to find the best and most efficient way to get the trailer loads to the site safely and on-time. This can get difficult, but we have an amazing dispatch team that makes sure we meet our deadlines.

Weather can play a big part in whether we can get on-site. Weather and storm systems can delay trucks because the roads cannot be traveled. Wind and storm systems can exist in areas where the model 16000 can be effective in wind corridors. We were recently going through tornado alley with our 18 loads, and needless to say, we had to slow things down and take more time to navigate the corridor. The roads that exist on wind parks and bluffs are not the best or easiest roads to maneuver. Any moisture can turn a dirt road into a challenging adventure.  The roads aren’t impossible to travel, but rather more difficult and time consuming for our crews.

Previous jobs or the next job can also set the tone of how we get a crane to a wind park.  If we are taking down a gearbox we can utilize a wide variety of cranes, but we are limited logistically. There is no telling where a crane will be in any given day or hour. Things can change so fast that one minute we have cranes available and 10 minutes later they are all booked and getting prepared to leave. Where we excel is in our experienced dispatch team. They are able to keep our cranes moving in and out of wind parks effectively and on-time all while keeping them busy the rest of the day. As I stated in previous columns, we can be “winded out,” which can further delay future projects within a wind park and outside. There are days when we are getting ready to leave the yard and get notification moments before we leave, that the wind has picked up and we are unable to work.

Crane erection time can be a challenge in wind parks, as well. When we are moving our crawlers, lattice boom truck cranes, or hydraulic cranes, the process or erection can vary. A typical hydraulic crane on a wind site may only take a few hours, but is limited to what parts it can hoist. The crawler crane can vary on erection time depending on which crawler we use. For our Manitowoc 2250, we can erect this model crane in as little as eight hours or it can take up to two to four days depending on other attachments we add to it, like the Max-er heavy lift attachment. For our Manitowoc model 16000 we can erect this crane in the same time frame as our 2250. Typically erection can take a day’s worth of work. Although, as previously stated, a number of factors can affect erection times. Building a crane on a wind site can also be difficult due to the lack of room to erect the crane.

Working in wind parks can be interesting and can keep our team of dispatchers busy. We are blessed to have a dedicated dispatch team that spans the Southwest. Having a team that not only works well with clients, but also is also highly skilled contributes to our success.

When our crawler cranes are moving at the rate they are – knowing the location is just as is crucial. In the grand scheme no one piece is more or less important than the other, but having an experienced dispatch team with more than 20 years experience means less time from call to delivery, which is beneficial to everybody. 

 

 

About The Author
Chris Martin

is marketing coordinator at Crane Service, Inc. Learn more at www.craneserviceinc.com.

 

 